Complete renovation of a 3,400 sf dental office. The scope of work consisted of updating the entire office area with new flooring, wall coverings, ceilings and paint.

During the renovation, all work was completed without interrupting patient care and the associated day to day operations of the office. In order to accommodate this schedule, work was phased so that only two (2) treatment rooms were impacted at any given time. MCCI worked closely with the owner and equipment vendor to coordinate removal of chair and specialty equipment. Finishes would then be replaced and the equipment reinstalled. Both treatment rooms were 100% complete before moving onto the next two rooms.

In some cases spaces were relocated and resized. The office's dental lab was one of the areas that was relocated as part of the project scope.